Construction works - 124 and 125-233 Scenic Road, Highton

13 March 2025

Between early-April 2025 and August 2025, construction works will occur to upgrade the infrastructure at our Montpellier Basin sites at 124 and 125-223 Scenic Road, Highton.

Initial works may involve hammering through rock over 3-4 days in mid-April, which can cause a significant amount of noise and dust. If rock hammering is required, we will aim to manage the impacts of this and apologise for the disruption.

As part of these works, please note:

  • Construction activities will occur Monday to Friday, between 7am and 6pm. If Saturday work is required, it will take place between 7am and 1pm.
  • During construction there may be increased noise and dust. We will aim to minimise impacts to local residents and businesses.
  • Access to private property for local residents, businesses, and emergency services will be maintained at all times.
  • Minor traffic management may be in place when large trucks are entering and exiting the sites along Scenic Road.
  • There’ll be no interruptions to water or sewerage services as part of these works.