About the project
Barwon Water is currently planning improvement works to the Queenscliff Feeder Main (water supply) along sections of the Bellarine Highway and into Point Lonsdale. These works will help increase year-round water capacity, ensuring Barwon Water can continue to provide high quality, affordable and secure services to our customers.
The Queenscliff Feeder Main (6.3 kilometres long) is the sole source of water supply for the customers in Queenscliff and Point Lonsdale and therefore it is crucial that it is in a good and reliable condition to maintain the current service levels and avoid future unplanned service interruptions to these towns.
Preliminary site investigations
We have now completed preliminary site investigations, including geotech investigations, cultural heritage and flora and fauna assessments and service proving,
Design stage site investigations
The design phase of the project is underway and we will be carrying out further site investigations over the coming months.
Stages of the project
Barwon Water will be replacing sections of the feeder main in stages over a period of approximately eighteen months.
See the below for a map of the location of works.
Section 1 - Fellows Road (220 meters)
Section 2 & 3 - Bellarine Highway (1,018 meters)
Section 4, 5, and 6 - Flinders Street (609 meters)
Section 7 - Henry Street to Stokes Street (987 meters)
Section 8 - King Street (400 meters)
Section 9 - Queenscliff Road (1000m)